C-5-0 FTA Capital Construction: Approve Subcontractors and Suppliers in B2GNow (B2GNow)

The C-5-0 FTA Capital Construction: Approve Subcontractors and Suppliers flowchart and process guides listed below outlines the responsibilities of the Prime Contractor, and Subrecipient Project Engineer/Project Manager for the approval of subcontractors and suppliers in B2GNow.
This is a graphic representation of the flowchart for C-5-0 FTA Capital Construction: Approve Subcontractors and Suppliers in B2GNow. Text version available below.
Flowchart C-5-0 FTA Capital Construction: Approve Subcontractors and Suppliers in B2GNow outlines the roles of the Prime Contractor and Subrecipient Project Engineer/Project Manager for entering and approving subcontractors and suppliers in B2GNow. Details and information provided in this flowchart is outlined below.


Download C-5-0 FTA Capital Construction: Approve Subcontractors and Suppliers in B2GNow Flowchart

Flowchart C-5-0 - FTA Capital Construction: Approve Subcontractors and Suppliers in B2GNow

  1. Start: The prime contractor identifies companies to bring on the contract (subcontractors or supplier).
  2. The prime contractor confirms the account creation for both the prime and subcontractors in B2GNow (Figure 5-1).
  3. The prime contractor determines if the firm will be performing as a subcontractor using the Sublet Permit Application, CDOT FTA Form 205, or supplier using the Supplier List, CDOT Form 1425, (Figure 5-2).
  4. The prime contractor completes the CDOT FTA Form 205 or CDOT Form 1425 and submits the form in B2GNow (Figure 5-3).
  5. The Subrecipient Project Engineer/Project Manager (PE/PM) personalizes the B2GNow dashboard (Figure 5-4A).
  6. The Subrecipient PE/PM reviews CDOT FTA Form 205 and 1425 to approve, deny, or return for update of the subcontractor and supplier in B2GNow (Figure 5-4).
  7. Decision Item: Was the CDOT FTA Form 205 or 1425 approved, returned for update or denied?
    • If approved, the subcontractor or supplier is now added to B2GNow. The process has ended.
    • If returned for update, go back to step 4.
    • If denied, the prime contractor will be required to enter a new application request in B2GNow and follow step 4.
  8. The process ends.

Process Guides

Graphic representation of a hard hat Contractors

Graphic representation of a work vest Subrecipient Project Engineer/Project Manager

  • 5-4 Review Form 205/1425 to Recommend Approval or Denial of Subcontractors/Suppliers in B2GNow (Project Engineer/Project Manager)
  • 5-4A Personalize the B2GNow Dashboard (Project Engineer/Project Manager)