C-6-0 FTA Capital Construction: Monitor Prompt Payment (B2GNow)
The C-6-0 FTA Capital Construction: Monitor Prompt Payment flowchart and process guides listed below outlines the responsibilities of the Subcontractor/Supplier, Prime Contractor and Subcontractors/Suppliers (with lower-tier Subcontractors/Suppliers), Subrecipient Project Engineer/Project Manager, and Civil Rights Business Resource Center within the prompt payment and B2GNow discipline area.
Download C-6-0 FTA Capital Construction: Monitor Prompt Payment Flowchart
Flowchart C-6-0 - FTA Capital Construction: Monitor Prompt Payment
- Start: The process of monitoring prompt payment occurs monthly on the project.
- The prime contractor and subcontractors/suppliers (with lower-tier subcontractors or suppliers) report monthly payments in B2GNow (Figure 6-1).
- The subcontractor and supplier confirms or disputes payment received during the audit period in B2GNow (Figure 6-2).
- Decision Item: Was there a discrepancy identified?
- If yes, continue to step 5.
- If no, continue to step 6.
- The prime contractor and subcontractors and suppliers (with lower-tier subcontractors/suppliers) respond to the discrepancy in B2GNow (Figure 6-3).
- The subcontractor or supplier responds to the discrepancy in B2GNow (Figure 6-4).
- The Subrecipient Project Engineer/Project Manager (PE/PM) conducts monthly monitoring of prompt payment, discrepancies, and resolving escalated issues (Figure 6-5).
- The Civil Rights Business Resource Center closes the overdue prompt payment audits in B2GNow (Figure 6-6).
- The process ends.
Process Guides
Prime Contractor and Sub-Prime
- 6-1 Prime Contractor and Subcontractors and Suppliers (with lower-tier Subcontractors and Suppliers) Report Monthly Payments in B2GNow (Prime Contractor, Subcontractor (Payors), and Supplier (Payors)
- 6-3 Prime Contractor and Subcontractors and Subcontractors (with lower-tier Subcontractors and Suppliers) Respond to Discrepancy in B2GNow
Subcontractors and Suppliers
- 6-2 Confirm or Dispute Payment Received During Audit Period in B2GNow (Subcontractor and Supplier)
- 6-4 Subcontractor and Supplier Responds to Discrepancy in B2GNow