C-2-0 FTA Capital Construction: B2GNow/LCPtracker Set Up
The C-2-0 FTA Capital Construction: B2GNow/LCPtracker Set UP flowchart and process guides listed on this page outlines the responsibilities of the Prime Contractor, Subrecipient and CDOT Civil Rights Business Resource Center within B2GNow and LCPtracker set up for a FTA capital construction project.
Download C-2-0 FTA Capital Construction: B2GNow/LCPtracker Set Up
Flowchart C-2-0 FTA Capital Construction: B2GNow/LCPtracker Set Up
- Start: The Subrecipient awards the contract to the Prime Contractor and provides a copy of the award to CDOT DTR.
- CDOT Division of Transit and Rail (DTR) provides a copy of the award to the CDOT Civil Rights Business Resource Center (CRBRC)
- The CRBRC confirms that the wage determination is
- The Subrecipient completes Sections I and II of the FTA Capital Construction Project Setup for B2GNow/LCPtracker form. (Figure 2-1)
- The Subrecipient provides the form to the Prime
- The Prime Contractor completes Section III of the FTA Capital Construction Project Setup for B2GNow/LCPtracker form (Figure 2-2).
- The Prime Contractor provides the completed form to the
- The Subrecipient reviews the form to ensure
- The Subrecipient provides the form to the
- The CRBRC sets up B2GNow and LCPtracker for the project (Figure 2-3).
- The process

Subrecipient
Prime Contractor