D-3-0 FTA Planning and Design: Monitor Prompt Payment (B2GNow)
The D-3-0 FTA Planning and Design: Monitor Prompt Payment flowchart and process guides listed below outlines the responsibilities of the Subrecipient, Prime Consultant and Sub-Prime Consultant (with lower-tier Subconsultants), Subrecipient Project Engineer/Project Manager, and Civil Rights Business Resource Center within the prompt payment and B2GNow discipline area.
Download D-3-0 FTA Planning and Design: Monitor Prompt Payment Flowchart
Flowchart D-3-0 - FTA Planning and Design: Monitor Prompt Payment
- Start: The process of monitoring prompt payment occurs monthly on the project.
- The Prime Consultant and Sub-Prime Consultant (with lower-tier subconsultants) report monthly payments in B2GNow (Figure 3-1).
- The subconsultant confirms or disputes payment received during the audit period in B2GNow (Figure 3-2).
- Decision Item: Was there a discrepancy identified?
- If yes, continue to step 5.
- If no, continue to step 6.
- The Prime Consultant and Sub-Prime Consultant (with lower-tier subconsultants) respond to the discrepancy in B2GNow (Figure 3-3).
- The subconsultant responds to the discrepancy in B2GNow (Figure 3-4).
- The Subrecipient Project Engineer/Project Manager (PE/PM) conducts monthly monitoring of prompt payment, discrepancies, and resolving escalated issues (Figure 3-5).
- The Civil Rights Business Resource Center closes the overdue prompt payment audits in B2GNow (Figure 3-6).
- The process ends.
Process Guides
Prime Consultant and Sub-Prime
- 3-1 Prime Consultants and Sub-Prime Consultants (with lower-tier Subconsultants) Report Monthly Payments in B2GNow
- 3-3 Prime Consultants and Sub-Prime Consultants (with lower-tier Subconsultants) Respond to Discrepancy in B2GNow
Subconsultants
- 3-2 Confirm or Dispute Payment Received During Audit Period in B2GNow
- 3-4 Subconsultant Responds to Discrepancy in B2GNow