October 13, 2015 - Northeastern Colorado/CDOT Region 4 - FORT COLLINS – During the day, potentially every day this week, travelers on Mulberry Bridge over the Poudre River will have to deal with the headache of one-lane traffic westbound into town. But that is needed so crews can prepare the road for what many Fort Collins residents have been waiting for: two-way traffic finally back!
News Releases
June 15, 2015 - Northeastern Colorado/CDOT Region 4 - FORT COLLINS – On Wednesday, June 17, a single-lane closure will be required on Mulberry Street between Lemay Avenue and Riverside Avenue.
May 14, 2015 - Northeastern Colorado/CDOT Region 4 - Mulberry Street, over the Poudre River, will be closed from 8 p.m. to 6 a.m. for five nights starting Monday, May 18, for girder installation for the second side of the new bridge.
March 19, 2015 - Northeastern Colorado/CDOT Region 4 - FORT COLLINS – A series of concrete and asphalt pavement pours are necessary to complete Phase 1 road work associated with new Mulberry Street bridge over the Cache la Poudre River.
February 12, 2015 - Northeastern Colorado/CDOT Region 4 - FORT COLLINS – Beginning on Monday, Feb. 16, pedestrian and bicycle traffic will be temporarily prohibited on Mulberry Street between Riverside Avenue and Lemay Avenue until late fall 2015 when new sidewalk is complete on the south side of the new SH 14 (Mulberry Street) bridge over the Cache la Poudre River.
December 19, 2014 - Northeastern Colorado/CDOT Region 4 - Westbound State Highway 14 (Mulberry Street) will stay open tonight. The Flatiron-led contractor team was able to finish bridge girder placement, which is a safety-critical operation, a night ahead of schedule.
December 8, 2014 - Northeastern Colorado/CDOT Region 4 - FORT COLLINS -- Beginning on Monday, Dec. 15, Mulberry Street will be closed from Lemay to Riverside from 8 p.m. to 6 a.m. the next day through Saturday morning to allow for the delivery and placement of girders for the new bridge over the Cache La Poudre River.
September 18, 2014 - Northeastern Colorado/CDOT Region 4 - The eastbound detour for the work to replace the Mulberry (State Highway 14) bridge over the Poudre River in Fort Collins will begin on Tuesday, Sept. 23, at 7 p.m.
September 15, 2014 - Northeastern Colorado/CDOT Region 4 - The work to begin replacing the Mulberry Street (State Highway 14) bridge over the Poudre River in Fort Collins will start this week with minimal impact on drivers. However, a major detour is planned to begin later this month that will be in place for the next year.