I-25 between 6th Avenue and 23rd Avenue
-
39.7389898615 -105.01404047
Project Owner | CDOT |
CDOT Region | 6 |
County | Denver |
Description of Work | Resurfaces approximately three miles of I-25 in asphalt. |
Estimated Total Project Cost | $4,259,920 |
ARRA Funds | $4,190,706 |
Project Status | Under Construction- In winter shutdown |
Start Date | June 14, 2009 |
Completion Date | April 2010 |
Percentage Spent | 76% |
Contractor | Brannan Sand and Gravel Co. |