Overview

Project Owner CDOT
CDOT Region 3
County Delta
Description of Work Reconstructs five miles of SH 92 in asphalt and adds passing lanes and shoulders to improve recreational bicycling.
Estimated Total Project Cost $9,837,484
ARRA Funds $9,667,646
Project Status Completed
Start Date July 13, 2009
Completion Date October 2010
Percentage Spent N/A
Contractor Tezak Equipment