US-40 Colfax Ave between Kipling St and Sheridan Blvd
- 
          
          
          
          39.740194365 -105.082683563
| Project Owner | CDOT | 
| CDOT Region | 6 | 
| County | Jefferson | 
| Description of Work | Resurfaces approximately three miles of US 40 in asphalt. | 
| Estimated Total Project Cost | $3,392,313 | 
| ARRA Funds | $3,337,195 | 
| Project Status | Construction Complete | 
| Start Date | June 1, 2009 | 
| Completion Date | September 2009 | 
| Percentage Spent | 100% | 
| Contractor | Asphalt Paving Co. | 