CO 83 Concrete Panel Replacement E-470 to Arapahoe Road

Project Facts

  • Cost: $2.1 Million
  • Contractor: R. L. Wadsworth
  • Timeline: February 2021 to June 2022
  • Location: CO 83 from E-470 to Arapahoe Road in Arapahoe and Douglas Counties

CO 83 Concrete Panel Replacement Project MapCO 83 Concrete Panel Project Limits

(Click image to enlarge)

About the Project:

The Colorado Department of Transportation and contractor, Ralph L. Wadsworth began work in February 2021 to improve several sections of roadway along CO 83 from E-470 to Arapahoe Road. This included removal and replacement of damaged concrete panels, ADA curb ramp improvements, signal work, sign and delineator installations and roadway joint sealing to minimize the effects of surface water infiltration.


Work Schedule & Traffic Impacts

Motorists can expect periodic lane closures along this corridor with minor traffic delays.

  • Daytime work consists of single lane closures from 6 a.m. to 3 p.m.
    Night work consists of double lane closures between the hours of 7 p.m. to 6 a.m.
  • Weekend work includes night time lane closures and single lane closures.
  • Variations to this may occur due to unforeseen circumstances and weather