US 287 & US 50 Resurfacing & Improvements in Lamar
Project Complete!
Construction will began in March 2021 on the improvements on US 287 in Lamar. The project will include concrete pavement overlay, relocating roadway lighting, removing and replacing raised medians, storm sewer improvements, new signing and lighting and ADA curb ramp improvements.
US 287 is heavily used by motorists and freight drivers and has not been repaves since 2004. This project will improve safety by replacing crumbling roadway and raised medians, improving lighting, replacing aging signing, improve ADA curb ramps, and widen shoulders in some areas.
Virtual Open House
View the project Virtual Open House Video
Project Facts
- Cost: $ 9,900,000
- Contractor: Scott Contracting
- Timeline: March 2021 - April 2024
- Location: US 287 through the City of Lamar and onto US 50