US 550 Coal Bank Pass
Completed in September 2016, this project added chip seal treatment on US 550 from the La Plata/San Juan County Line, from mile post 49.84 to mile post 55.95.
While repairing this 11-year-old surface, crews:
- removed bumps and wheel ruts for smoother rides.
- installed new runaway vehicle/truck ramp signage.
- installed new guardrails.
- installed new solar-powered/-lighted "Caution: Sharp Curve" signs.
Project Facts
-
Cost:
$2.8 million
Improvement Area
- 6 miles