US 285 at Shaffers Crossing
-
39.4792680603 -105.369400978
| Project Owner | CDOT |
| CDOT Region | 1 |
| County | Jefferson |
| Description of Work | Constructs a grade-separated interchange at Elk Creek Road, new frontage roads and a wildlife crossing underpass. When complete, Elk Creek Rd. will run under US 285. |
| Estimated Total Project Cost | $10,850,000 |
| ARRA Funds | $8,400,000 |
| Project Status | Under Construction |
| Start Date | September 14, 2009 |
| Completion Date | September 30, 2011 |
| Percentage Spent | N/A |
| Contractor | Hudick Excavating |