I-70 Mountain Express Lane

Project Complete

Project Overview

The I-70 Mountain Express Lane — the outcome of the peak-period shoulder lane (PPSL) project — runs eastbound on I-70 from Empire through the Veterans Memorial Tunnels to Idaho Springs. The lane is only open weekends and holidays, and is a shoulder lane when not in use.

A part of CDOT's comprehensive plan to improve travel in the I-70 Mountain Corridor, this project upgraded 13 miles of eastbound I-70 within CDOT's existing right-of-way. The upgrades created the I-70 Mountain Express Lane—a wide shoulder that, only during peak travel periods, operates as a third travel lane.

The I-70 Mountain Express Lane is dynamically priced to keep traffic moving. Prices fall when CDOT wants to encourage drivers to use the lane and increase as the lane reaches capacity. Learn more about how Express lanes Operate.

Using the shoulder to create an express lane within the existing I-70 right-of-way during peak periods instead of adding a full lane has several benefits.

For long-term information on traffic conditions along the I-70 mountain corridor, travelers can sign up for text or email alerts, visit COtrip.org, or call 511.


Background

The I-70 Mountain Express Lane project upgraded 13 miles of eastbound I-70 within CDOT's existing right-of-way. This work created a wide shoulder that operates as a third travel lane along eastbound I-70 from Empire through the Veterans Memorial Tunnels to Idaho Springs.

Rather than being open all the time, the lane is open for up to 100 days per year when the highway experiences the highest traffic congestion (primarily holidays and weekends). This provides much-needed relief to the busiest recreation highway in the state. When the lane is not open, the overhead signage indicates that it's closed and is being used as a shoulder.

Since opening in December 2015, the Mountain Express Lane has relieved traffic congestion, diverting 750 to 900 cars from the free general-purpose lanes. This alleviates traffic congestion in the Express Lane, and decreases congestion in general-purpose lanes and frontage roads. The lane reduces travel time by nearly half from the Eisenhower/Johnson Memorial Tunnels to the top of Floyd Hill, resulting in an average time savings of 30 minutes.

CDOT, local communities and travelers are benefitting from the I-70 Mountain Express Lane via decreased travel times and faster, more consistent speeds. The lane has also helped reduce congestion due to traffic incidents.


Project benefits

  • Dynamic toll pricing keeps traffic moving; prices fall to encourage drivers to use the lane and rise as the lane reaches capacity.
  • Reduces travel time by nearly half from the Eisenhower/Johnson Memorial Tunnels to the top of Floyd Hill, resulting in an average 30-minute time savings
  • Provides drivers with the choice of a new, more reliable travel lane
  • Avoids overbuilding I-70 by using the shoulder as a third lane during peak hours
  • Enhances recent Twin Tunnels (Veterans Memorial Tunnels) improvements
  • Allows for faster speeds in all lanes, thus decreasing overall travel time

Project Schedule

Construction of the I-70 Mountain Express Lane is slated to be completed by the start of the 2015/2016 ski season. The table below shows an estimated project schedule, though the schedule may vary as weather permits.

Fall 2014 – Summer 2015

Shoulder improvements

*Fall/Winter 2014

Reconstruction of the SH-103 Bridge and Upgrades to Exit 240

*Spring 2015

Initial improvements to Charlie Tayler Water Wheel Park

Spring/Summer 2015

Reconstruction of Exit 241
Reconstruct each of the on-ramps and off-ramps in the Exit 240 (SH 103) interchange 

Summer/Fall 2015

Signage installation and testing

Fall 2015

I-70 Mountain Express Lane Opens

*weather permitting


Prior to the I-70 Mountain Express Lane opening, traffic on eastbound I-70 between US 40/Empire Junction and the Twin Tunnels could be delayed up to 2.5 hours for an eight-mile stretch.

Crews on this project expanded eastbound I-70 from two lanes to three between Idaho Springs and Empire. That additional lane—the shoulder of the interstate—now functions as a tolled Express Lane in which motorists can travel during designated times, determined by traffic volumes.

  • During normal traffic, the Express Lane serves as a shoulder.
  • Improved signage alerts motorists when the Express Lane is open.

Since opening, this and other Express Lanes across the state have moved people and goods faster during peak travel times.

Exit 241 Reconfiguration

Work to reconfigure the Exit 241 interchange and rebuild the Colorado Boulevard Bridge over I-70 started in April 2015 and was completed in fall 2015.

The new bridge structure was built immediately east of the existing structure, which remained open to traffic until vehicles were moved onto the new structure in fall 2015.

CO 103 Bridge Reconstruction

The Colorado Highway (CO) 103 Bridge over I-70 reopened to traffic in February 2015. Reconstruction of each of the on-ramps and off-ramps in this interchange began in late April.

The bridge itself over I-70 will remain open to vehicles and crews will rebuild these ramps in phases to keep traffic moving through a portion of the interchange. These phased closures, their anticipated duration and the associated detours are as follows:

  • The new westbound I-70 off-ramp to CO 103 (Exit 240) will be built adjacent to the existing off-ramp to maintain access to the downtown Idaho Springs Business and Historic District
  • Reconstruction of the CO 103 on-ramp to westbound I-70 is complete
  • Reconstruction of the CO 103 on-ramp to eastbound I-70 is complete
  • Reconstruction of the eastbound I-70 off-ramp to CO 103 is complete

Corridor-Wide Improvements

The eastbound I-70 Peak Period Shoulder Lane (PPSL) project is part of a comprehensive set of solutions to reduce congestion and improve safety in the I-70 Mountain Corridor. Among the other recent and near-term improvements that will help the corridor are widening and expanding the Twin Tunnels’ (Veterans Memorial Tunnels) eastbound bore to three lanes (completed in December 2013) and widening the Twin Tunnels’ (Veterans Memorial Tunnel) westbound bore (completed in December 2014).

Other improvements that have been prioritized for implementation in the corridor when funding is secured include studying and implementing a westbound Peak Period Shoulder Lane and making a number of improvements to westbound I-70 from Floyd Hill to Idaho Springs.

Once CDOT implements these projects more progress will have been made to improve this section of the I-70 Mountain Corridor than has been accomplished in decades.

This is all part of much larger plan to solve the I-70 issues in a cooperative, consensus-based manner. In June 2011, the U.S. Department of Transportation issued a Record of Decision (ROD) outlining a number of actions to address I-70 congestion and provides a path forward to improving mobility along the corridor.  Numerous projects along I-70 have begun and are working cohesively with one another in an effort to realize the vision for a more efficient I-70.

To learn more about other projects in the I-70 Mountain Corridor, visit CDOT’s I-70 Mountain Corridor project webpage.

A critical element of the I-70 Mountain Express Lane planning process was the ability to foster an ongoing dialogue with representatives of the local community by collecting input from key community members and stakeholders alike. Their valuable insight continues to serve as a meaningful resource during the construction phase of the project. Project Leadership and the Technical Teams were formed during the planning phase of the project and will continue to meet periodically through construction to ensure that their concerns are addressed throughout the remainder of the project. In addition, issue-specific task forces (e.g. Exit 241 Interchange reconfiguration) have and will continue to meet.

Organizations represented on the Project Leadership Team and Technical team are:

City of Idaho Springs Federal Highway Administration
Clear Creek County High Performance Transportation Enterprise
Clear Creek County Sheriff's Department I-70 Coalition
Clear Creek Watershed Foundation Idaho Springs Police Department
Colorado Department of Transportation Jefferson County
Colorado Motor Carriers Association Summit County
Colorado State Historic Preservation Office US Army Corps of Engineers
Colorado State Patrol US Forest Service
Colorado Trout Unlimited Upper Clear Creek Watershed Association
Colorado Parks and Wildlife

The I-70 Peak Period Shoulder Lane (PPSL) Project proposes to expand select areas of eastbound I-70 to accommodate a wide shoulder that can be used as an additional travel lane during peak travel times.  The PPSL will be tolled during these peak times to provide a more consistent and reliable travel time in the corridor and will function as a shoulder/breakdown area during non-peak times.  The existing two general purpose lanes will remain free at all times as they are today.  The PPSL Project will also include the replacement of two deficient bridges over I-70 at exits 240 and 241 with minor interchange improvements at each location.  The project is located in Clear Creek County on Interstate 70 from the US 40 Interchange at milepost 232 to the Twin Tunnels at milepost 242.  The project is considered an operational interim solution in the corridor and an expanded use of the existing transportation infrastructure as defined in the 2011 Programmatic Environmental Impact Study (PEIS) and Record of Decision (ROD) Preferred Alternate Minimum Program.

The Peak Period Shoulder Lane Project construction is scheduled to begin June 26, 2014 with a projected PPSL opening date in fall of 2015.