US 6 & 20 Road Intersection Improvements
Project Complete
About the Project
Widening and partial reconstruction of the intersection of US Highway 6 and 20 Road near Fruita. The existing intersection is offset, and the new intersection will realign the northbound approach of 20 Road to US 6 to align with the southbound approach. The intersection will be signalized with dedicated turn lanes. Other elements of the project include the reconstruction of a portion or River Rd. at the tie in to the intersection. The alignment and high speeds create difficulties for left-turning vehicles.
Project Benefits
- Realign 20 Road to remove the offset alignment and upgrade the railroad gates and signal at this location
- This intersection has historically had high motor vehicle crash data
- The project is a safety improvement with the addition of a signalized intersection and the roadway realignment
Work Schedule
- Work will last approximately five months from April 2023 through end of December 2023.
- Working hours are Monday to Friday, 7 a.m. to 7 p.m.
Traffic Impacts
Motorists can expect the following impacts during the period of construction:
- Traffic impacts will include closing 20 Road for an extended period of time while the work is completed. The recommended detour in place is:19 Road (north) to J Road (east) to 22 Road (south)
- Motorists can expect single lane and shoulder closures in both the westbound and eastbound direction through the project work zone which stretches about one-eighth of a mile at the intersection of 20 Road
- Speeds through the work are reduced to 40 mph
- 12-foot width restriction for commercial vehicles
- Signs will be posted to alert motorists to the closures and available detour routes
Refer to COtrip.org for real-time travel conditions and road closures
Project Facts
- Cost: $3.7 million
- Contractor: United Companies
- Timeline: April 2023through end of December 2023
- Location: Intersection of US 6 & 20 Road just inside the City of Fruita limits
- Mile Posts: 23.18 - 23.97
- County: Mesa