Bridge Guardrail Replacement near Boulder and Deer Trail
About the Project
The work includes:
- Removal and replacement of the bridge guardrail
- Replacing the signage
Work this Week & Lane Closures for Bridge Guardrail Replacement near Boulder & Deer Trail
Project Facts
- Construction Cost: $612,588
- Contractor: ABCO Contracting
- Timeline: March 2026 to June 2026
- Location: CO 157 and I-70
- Nearest Towns/Cities: Deer Trail and Boulder
- Mile Point(s): MP 329.67 to MP 3.52
- Counties: Arapahoe and Boulder
Project Benefits
Updating the bridge rails at these two locations which will make the bridges safer for the traveling public.
Work Schedule
To be announced.
Traffic Impacts
- To be announced
- Refer to COtrip.org for real-time travel conditions and road closures