CO 165 Bridge Replacement
About the Project
The work includes:
- Place a concrete bridge culvert at the realigned Willis Creek channel location
- Replace the corrugated culverts at the site of the existing Willis Creek crossing
Project Facts
- Construction Cost: To be announced
- Contractor: Siete, Inc.
- Timeline: October 2026 to April 2027
- Location: CO 165
- Nearest Town/City: Colorado City
- Mile Point(s): MP 16.3 to MP 16.43
- County: Custer
Project Benefits
- Essential to motorists and emergency responders in Custer and Pueblo counties traveling the CO 165 corridor
- Integral part of CDOT’s response to the Aspen Acres Fire
Work Schedule
- Daytime work hours range from 7 a.m. to 5:30 p.m., Monday through Friday
- Work is anticipated to be completed in late April 2027
Traffic Impacts
- Vehicles will be reduced to a single lane, with alternating traffic intermittently in either direction, throughout the duration of the project, guided by temporary signals
- Lane closures, guided by flaggers, will have up to 15-minute delays
- Speed limit will be reduced to 40 mph through the work zone
- Refer to COtrip.org for real-time travel conditions and road closures