CO 66 Intersection Improvements in Northeastern Colorado/Region 4
Starting on April 13th as final grading, seeding, & restoration is taking place, there are no anticipated traffic impacts for the remainder of the project. The hotline and project email will be monitored once a week on Thursdays and any outreach from the public will be addressed at that time.
About the Project:
CO 66 at Weld County Road (WCR) 7 and WCR 13 Intersection Improvements. This intersection improvement project includes two intersections. The traffic signal systems at both intersections will be replaced. Work at WCR 7 will also consist of adding a northbound left turn lane, and overlaying the entire intersection including new lanes a development is adding. The work will consist of minor earthwork, hot mix asphalt (HMA), traffic signals, bored conduit, signing, striping and traffic control.
Project Benefits
- Upgrades improve traffic flow for motorists and enhance pedestrian safety at crosswalks
- A new, smooth surface element that could be encountered by pedestrians that may cause trips or falls
- The new signal system is being installed to accommodate future widening of both CO 66 and the Weld County Roads (WCR 7 & WCR 13)
Work Schedule:
- Construction will begin on October 16, 2023
- Working hours are Monday through Friday from 8 a.m. to 5 p.m.
- The project is anticipated to end in late May 2024.
Work this Week & Lane Closures CO 66 Intersection Improvements
Project Facts
- Construction Cost: $2.3 million
- Contractor: Brannan Sand & Gravel
- Timeline: October 16, 2023 to end of May 2024
(Delay due to weather-related winter closures) - Location: Intersection at CO 66 and WCR 7 along with the intersection at CO 66 and Colorado Boulevard
- Nearest Town/City: Outside Longmont
- Mile Point(s): 41.36 to 45.10
- County: Weld