Project Schedule

CO 83 Project Schedule Revised

  • Existing Conditions Analysis & Safety Analysis: March through September 2021
  • Public Engagement: September through October 2021
  • Solution Identification: August through November 2021
  • Project Prioritization: October 2021 through February 2022
  • Public Engagement: Fall 2022
  • Early Packages (signing, striping, signal timing): Construction beginning in 2022
  • Recommended Packages A Through M (Phase II): Anticipated schedules will be updated as funding is approved. At least one package from the Recommended Projects Summary (Packages A-M) is expected to begin construction in 2023.