CO 86 Resurfacing
About the Project
Paving work will take place in the town of Elizabeth from Mile Points 15.3 to 16.3. The work will include mill and fill operations by grinding down and recycling the top layer of asphalt, and then placing a new layer of fresh asphalt on top of the roadway.
Work this Week & Lane Closures for CO 86 Resurfacing
Project Facts
- Construction Cost: $1.4 million
- Contractor: Brannan Sand and Gravel LLC
- Timeline: June 2026 to August 2026
- Location: CO 86
- Nearest Town/City: Elizabeth
- Mile Point(s): MP 15.3 to MP 16.3
- County: Elbert
Project Benefits
- Prolong the life of the road surface
- Provide a smoother road surface
- Add durability by increasing the resistance of ruts and road damage
- Smoother and safer drive for motorists
Work Schedule
- Normal working hours will range from 7 a.m. to 5 p.m., Monday through Friday
- Night work is anticipated from Sunday, June 14, through Monday, June 29, with working hours from 7 p.m. to 6 a.m.
Traffic Impacts
- Shoulder closures and limited lane closures will be in place when needed throughout the project
- Lane closures will have up to 15-minute delays