CO 94 Eastern Plains Resurfacing
About the Project
Work will include:
- A two-inch asphalt overlay
- Rumble strip installation
- Striping
Work this Week & Lane Closures for CO 94 Eastern Plains Resurfacing
Project Facts
- Construction Cost: $12.3 million
- Contractor: Martin Marietta
- Timeline: July 2026 to December 2026
- Location: CO 94
- Nearest Town/City: Rush and Aroya
- Mile Point(s): MP 35 to MP 76
- County: Lincoln
Project Benefits
The new asphalt will provide the following benefits:
- Add years of life to the highway
- Provide a smoother road surface
- Add durability by increasing the resistance of ruts and road damage
Work Schedule
- Daytime work hours are one-half hour after sunrise and until one-half hour before sunset, Monday through Friday.
Traffic Impacts
Motorists can expect the following impacts during the period of construction:
- One-lane alternating traffic
- Up to 15-minute delays
- 12-foot width restriction
- Speed reduced to 35 MPH
- Refer to COtrip.org for real-time travel conditions and road closures