I-225 Bridge Rehabilitation at 6th & 2nd Avenues

About the Project

The I-225 Bridge Rehabilitation at 6th and 2nd avenues improved the driving surface of the northbound and southbound I-225 bridges over 2nd and 6th avenues. These bridges had an elevated slope in the middle, and this project helped flatten the driving surface by putting down asphalt between the middle of the bridge and the approaches to each bridge.

Along with leveling out the lanes, this project included:

  • Replacing the bridge expansion joints with plug joints
  • Replacing several concrete panels in both directions of I-225 just north of 6th Avenue
  • Installing a waterproof overlay
  • Strategic mill and overlay
    • The overlay involves putting down gradually decreasing depths of asphalt from the middle of the bridge to the bridge approaches to even out the roadway surface

Work this Week & Lane Closure on I-225 Bridge over 2nd & 6th Avenues

Project Facts

  • Construction Cost: $2.8 million
  • Contractor: Structures Inc.
  • Timeline: August 2025 to November 2025
  • Location: I-225
    • Nearest Town/City: Aurora
    • Mile Point(s): MP 9.5 to MP 7.5
    • County: Arapahoe
Map of I-225 bridge rehabilitation project area along I-225 from 6th to Alameda avenues
Map of I-225 bridge rehabilitation project area along I-225 from 6th to Alameda avenues.

Project Benefits

Improved and flattened the driving surface of the northbound and southbound I-225 bridges over 2nd and 6th avenues.


Work Schedule

  • The project began work on Aug. 10, 2025 and reached substantial completion on Nov. 25, 2025.

Traffic Impacts

  • Construction schedules can change depending on weather and other factors
  • Refer to COtrip.org for real-time travel conditions and road closures