Temporary Barrier on I-270
About the Project
This project will be setting up temporary pinned barrier in front of the bridge railing on bridge decks over South Platte, Burlington Ditch, Union Pacific Railroad (UPRR) and Burlington Northern Santa Fe (BNSF).
Project Facts
- Construction Cost: $1.3 million
- Contractor: Kiewit
- Timeline: October 2025 to November 2025
- Location: I-270
- Nearest Town/City: Commerce City
- Mile Point(s): MP 0 to MP 3
- County: Adams
Project Benefits
Placing pinned barrier in front of the bridge deck railing improves safety until the main I-270 project begins.
Work Schedule
- Sunday through Thursday, 10 p.m. to 5 a.m.
Traffic Impacts
- To be announced.
- Refer to COtrip.org for real-time travel conditions and road closures