I-70 Eisenhower-Johnson Memorial Tunnels Resurfacing
About the Project
The project will remove the existing pavement on the right lanes in both of the Eisenhower-Johnson Memorial Tunnels on I-70 and replace it with new asphalt. Work will also include restriping the lanes.
Work this Week & Lane Closures for I-70 EJMT Resurfacing
Project Facts
- Construction Cost: $2.75 million
- Contractor: Brannan Sand & Gravel
- Timeline: September 2025 to October 2025
- Location: I-70 Eisenhower-Johnson Memorial Tunnel
- Nearest Town/City: Silverthorne
- Mile Point(s): MP 213.5 to MP 215.7
- Counties: Clear Creek and Summit

Project Benefits
- Remove rutting
- Extend asphalts' lifespan
- Improve pavement condition
- Add a safer driving experience before winter hits
Work Schedule
- Work will last approximately two months
- Sunday, Sept. 14, 2025 through end of September 2025:
- 9 p.m. to 6 a.m. on Sundays
- 8 p.m. to 5 a.m. Mondays to Thursdays
- Oct. 1, 2025 through end of October 2025:
- 8 p.m. to 5 a.m. Sundays to Thursdays
Traffic Impacts
Motorists can expect the following impacts during the period of construction:
- Both directions of I-70 traffic will be held at the entrance of the tunnel for up to 30 minutes while one direction of travel at a time is escorted through the tunnel safely.
- Drivers are urged to obey the posted speed limit, leave plenty of following space, watch for crews and equipment and pay extra attention during this overnight work.
- Refer to COtrip.org for real-time travel conditions and road closures