South Central Colorado Bridge Preventative Maintenance

About the Project

The project locations include:

  • O-13-B (US 160 MP 233.61) over the Rio Grande in Alamosa
  • I-12-T (US 24 MP 213.43) over the Arkansas
  • I-13-D (US 24 MP 221.52) over Trout Creek

Structure: O-13-B (Alamosa County)

  • Location: US 160 bridge over the Rio Grande in the City of Alamosa, MP 233.61
  • Work includes full mill of asphalt over the top of the bridge, class three deck patching, replace 0-4 expansion joints on both ends of the bridge, new waterproofing membrane, HMA overlay of bridge, restore pavement markings and repair sidewalk approach in northeast corner of bridge

Structure: I-12-T (Chaffee County)

  • Location: US 24 bridge over the Arkansas, just east of Johnson Village, MP 213.43
  • Work includes:
    • Class two and class three removal, deck patching, remove sliding plate expansion joint at pier 5 and replace with 0 to 4 expansion joint
    • Install waterproofing membrane and HMA asphalt overlay, saw and seal joints, and restore pavement markings
    • Install Bridge Rail Type Three Special (three beam) on the existing dog house rail with transitions to new approach rail
    • Replace existing approach rail on the west side of the structure
    • Add a new approach rail to the east side of the structure
    • Guardrail will be galvanized

Structure: I-13-D (Chaffee County)

  • Location: US 24 bridge over Trout Creek, eight miles east of Johnson Village, MP 221.52
  • Work includes:
    • Remove the joints over the piers, install waterproofing membrane over the joints, patch with HMA and restore the pavement markings
    • Patch underneath the structure on the pier cap and pier columns
    • Replace all existing approach rail with galvanized guardrail

Project Facts

  • Construction Cost: $2.16 million
  • Contractor: ABCO Contracting, Inc.
  • Timeline: May 2026 to October 2026
  • Location: US 160 and US 24
    • Nearest Towns/Cities: Alamosa and Johnson Village
    • Mile Point(s): MP 233.61 to MP 221.52
    • Counties: Alamosa and Chaffee

Project Locations

Johnson Village Bridge Location Map
Johnson Village Bridge Location Map
Alamosa Bridge Location Map
Alamosa Bridge Location Map
Trout Creek Bridge Location Map
Trout Creek Bridge Location Map

Project Benefits

Benefits for motorists from these maintenance repairs include:

  • Smoother, more comfortable road surface, making travel safer for vehicles, especially in inclement weather
  • Better drainage and weather resilience, preventing clogging from debris and helping avoid water pooling, hydroplaning risks or flooding
  • Extended lifespan of existing structures, potentially delaying or avoiding more extensive and disruptive repairs or full replacements
  • Repaired and updated joints improve infrastructure efficiency and environmental impacts

Work Schedule

Daytime work hours range from 7 a.m. to 5 p.m., Monday through Friday.


Traffic Impacts

  • US 160 bridge over the Rio Grande river will be reduced to one lane of alternating traffic until early June
    • A width limit of 10 feet 0 inches will be in effect.
  • Motorists should plan for lane shifts and lane reductions
  • Two-way traffic will be maintained throughout the project
  • Debris removal will be conducted so that the traveling public is protected and traffic impacts are minimized
  • Motorists are advised to drive with extreme caution through these areas as the travel lanes will be narrower and crews with heavy equipment will be working in the area
  • Minor traffic delays are expected
  • Refer to COtrip.org for real-time travel conditions and road closures