Southeastern Colorado Striping
About the Project
Crews will remove existing pavement markings and add new striping and markings. The project is expected to have a winter shutdown and work is anticipated to be complete in June 2026.
The project will take place in multiple counties, including:
- El Paso
- Huerfano
- Las Animas
- Park
- Pueblo
- Summit
- Teller
Crews will perform work on the following highways:
- CO 9 between Fairplay and Breckenridge (Mile Point 64.91 to MP 80.3)
- CO 12 from La Veta to Trinidad (MP 0 to 70.757)
- CO 78 southwest of Pueblo (MP 31.79 to MP 33.27)
- CO 94 east of Colorado Springs (MP 0.548 to MP 17.10)
- CO 96 Pueblo (MP 50.303 to MP 58.812)
- CO 105 Monument (MP 4.731 to 6)
- CO 115 south of Colorado Springs (MP 38.952 to MP 41.957)
- I-25 between Larkspur and Trinidad (MP 26.6 to MP 164)
- US 24 between Buena Vista and Colorado Springs (MP 225.57 to MP 303.43
- US 285 from Fairplay south (MP 161.79 to MP 182.5)
- US 50 from the intersection at I-25 in Pueblo to Pueblo West (MP 209.267 to MP 314.598)
Work this Week & Lane Closure for Southeastern Colorado Striping
Project Facts
- Construction Cost: $3.5 million
- Contractor: Road Safe Traffic
- Timeline: August 2025 to June 2026
- Locations: CO 9, CO 12, CO 78, CO 94, CO 96, CO 105, CO 115, I-25, US 24, US 285 and US 50
- Nearest Towns/Cities: Fairplay, Colorado Springs and Pueblo
- Mile Point(s): MP 266 to MP 164 (refer to the About the Project for specifics)
- Counties: El Paso, Huerfano, Las Animas, Park, Pueblo, Summit and Teller
Project Locations



Project Benefits
The pavement striping and markings will make traveling conditions safer providing brighter, more visible lines.
Work Schedule
- Crews will start at the CO 9, US 285 and US 24 locations
- In September 2025, crews will work on the following locations:
- Colorado Springs (US 94 and CO 115)
- Pueblo (US 50, CO 96 and CO 78)
- Sunday through Thursday nights, work will take place from 7 p.m. to 7 a.m.
Traffic Impacts
Motorists can expect the following impacts during the period of construction:
- Various mobile lane closures will take place within the work zones with reduced speeds
- Plan ahead and expect short delays
- This is a swift moving, mobile operation; although work zones will only be in place for a few hours, motorists are urged to use caution and watch for heavy equipment
- Through lanes and turn lanes may be temporarily closed to traffic causing brief travel delays
- Travelers are discouraged from passing the striping truck and crossing over fresh paint, as this may damage a vehicle’s finish. Please drive with patience during striping operations
- Construction schedules could change depending on the weather
- Refer to COtrip.org for real-time travel conditions and road closures