Southeast Colorado Timber Bridge Repair
About the Project
This project is located in various counties within the southern Colorado region. Project work consists of timber bridge retrofitting of structures on various roadways in the region.
Work this Week & Lane Closures
<project name>
Project Facts
- Construction Cost: $1.08 million
- Contractor: TLM Constructors
- Timeline: April 2026 to October 2026
- Location: CO 10, CO 96, CO165, CO 202, CO 69, US 50 and US 350
- Nearest Town/City: Pueblo
- Mile Point(s): MP 2.044, MP 13.347, MP 24.337, MP 27.498, MP 30.022, MP 32.65, MP 33.111, MP 33.343, MP 346.998, MP 382.754, MP 43.030, MP 46.105 and MP 61.764
- Counties: Custer, Huerfano, Las Animas, Otero and Pueblo
Project Benefits
The bridge enhancements will provide safer travel ways for the public.
Work Schedule
To be announced.
Traffic Impacts
- To be announced