US 385 Resurfacing North of Cheyenne Wells

Project Complete!

This was a resurfacing and safety improvement project on a 16-mile stretch of U.S. Highway 385 north of Cheyenne Wells. Work included adding up to six inches of new asphalt along the project corridor, repairing a bridge deck, performing full depth reclamation on over three miles of highway, and making other safety improvements.

Newly resurfaced section of US 385 north of Cheyenne Wells

Work this Week & Lane Closures
US 385 Resurfacing North of Cheyenne Wells

Project Facts

  • Cost: $13.5 Million
  • Contractor: A&S Construction
  • Timeline: September 2022 to July 2023 with a winter shutdown from December 8, 2022 to April 24, 2023
  • Location:  US 385
    • City: north of Cheyenne Wells
    • Mile Points:  172.7 - 156.8
    • County:  Kit Carson, Cheyenne

Cheyenne Wells project map