US 40/CO 13 Signals Replacement in Craig
About the Project
This project is located within the city limits of Craig, Colo. and includes the replacement, reconstruction and upgrades of traffic signals at two intersections:
- The replacement and reconstruction of the existing traffic signal at the intersection of Yampa Avenue (CO 13) and 9th Street. The reconstruction will include:
- New traffic signal equipment
- New pedestrian equipment
- Curb ramps
- The project also includes traffic signal equipment upgrades of the intersection of 4th Street (US 40) and Ranney Street. This upgrade will include:
- New traffic signals
- Pedestrian equipment
Work this Week & Lane Closures on US 40/CO 13 in Craig
Project Facts
- Construction Cost: $1.1 million
- Contractor: Sturgeon Electric
- Timeline: June 2025 to August 2025
- Location: US 40 and CO 13
- Nearest Town/City: Craig
- Mile Point(s): MP 90.53
- County: Moffat

Project Benefits
Traffic signal improvements to these intersections, including:
- Improve traffic flow for motorists
- Enhance pedestrian safety at crosswalks
Work Schedule
- Normal working hours will be Monday through Friday 7 a.m. to 7 p.m.
- There will be no work on weekends or holidays
- Project is scheduled to begin June 9
- Project completion is expected in late August
- Night work is possible, but will be announced, if necessary
Traffic Impacts
Motorists can expect the following impacts during the period of construction:
- At the intersection of West 4th Street and Ranney Street (US 40), traffic may be reduced to one lane during work hours
- Refer to COtrip.org for real-time travel conditions and road closures