US 50 Culverts Repairs in Cañon City
About the Project
The Colorado Department of Transportation will begin a culvert repair project on Dec. 8, 2025 along US Highway 50 in Canon City. Work will take place east of downtown on a two-mile stretch of highway from 15th Street to Justice Center Road at mile points 279.33 to 281.65.
The work will include the relining of 34 culverts along a two-mile stretch of US 50, using pipe rehabilitation by ultraviolet (UV) light glass reinforced using a Cured-In-Place Pipe (CIPP) process.
Work this Week & Lane Closures for US 50 Culvert Repair in Cañon City
Project Facts
- Construction Cost: $1.45 million
- Contractor: Instituform Technologies, LLC
- Timeline: December 2025 to March 2026
- Location: US 50
- Nearest Town/City: Cañon City
- Mile Point(s): MP 279.33 to MP 281.65
- County: Fremont
Project Benefits
- Accommodate higher accumulations of rainfall
- Lower the risks associated with such instances as flooding
- Maintain safe driving conditions
Work Schedule
- Daytime work hours range from 7 a.m. to 7 p.m., Monday through Friday
Traffic Impacts
- Vehicles will be reduced to a single-lane
- Alternating traffic will occur intermittently in both directions
- Various shoulder closures will also take place
- Lane closures, guided by flaggers, could result in short delays
- Refer to COtrip.org for real-time travel conditions and road closures