US 50 Resurfacing in Pueblo West
About the Project
Work will include:
- Milling old asphalt
- Paving with new asphalt
- Bridge repairs
- Guardrail replacement
Work this Week & Lane Closures for US 50 Resurfacing in Pueblo West
Project Facts
- Construction Cost: $12.3 million
- Contractor: Martin Marietta
- Timeline: April 2026 to October 2026
- Location: US 50
- Nearest Town/City: Pueblo West
- Mile Point(s): MP 296.2 to MP 309.3
- County: Pueblo
Project Benefits
- The new asphalt adds approximately 10 years of life to the highway
- Provides a smoother road surface for motorists
- The new guardrails stand 31 inches high
- Meets new safety standard requirements
- Helps veering vehicles remain on the road more effectively
- Provides safer highway for the traveling public
Work Schedule
- Daytime work hours are one half hour after sunrise and until one half hour before sunset Monday through Friday.
- Nighttime work hours are from 8 p.m. to 6 a.m. Sunday night through Friday morning.
Traffic Impacts
- Single lane and shoulder closures will take place in the work zone
- 15-foot width restriction
- The speed limit will be reduced to 55 mph in the work zone
- Construction schedules are weather dependent
- Refer to COtrip.org for real-time travel conditions and road closures