Two overnight westbound I-70 closures at US 6 for segmental bridge construction

Travel Advisory

Nov. 19, 2026 - Clear Creek County - Motorists will detour using the US 6 (Exit 244) off- and on-ramps

Clear Creek County - The I-70 Floyd Hill Project will require two overnight closures of westbound Interstate 70 as major progress continues on the construction of “The Live Lift,” the westbound I-70 concrete cast-in-place segmental bridge. Crews will grout the tendons – which delivers a protective seal to the bridge, providing a longer lifespan and smoother ride for motorists upon completion – on the concrete segments of the cast-in-place segmental bridge over westbound I-70 near US Highway 6.

This work will require two overnight closures of westbound I-70 at US 6 (Exit 244). Motorists can sign up for text alerts by texting floydhill (one word) to 21000 to stay informed on the upcoming closures.

Full closures of westbound I-70 at US 6

Crews will require two overnight closures of westbound I-70 at US 6 (Exit 244).

  • 9 p.m., Sunday, Nov. 22, to 5 a.m., Monday, Nov. 23
  • 9 p.m., Monday, Nov. 23, to 5 a.m., Tuesday, Nov. 24

Detour: Westbound I-70 motorists will merge into one lane and use the US 6 (Exit 244) off- and on-ramps to continue on westbound I-70.

A map depicting how Westbound I-70 motorists will merge into one lane and use the US 6 (Exit 244) off- and on-ramps to continue on westbound I-70.
Westbound I-70 motorists will merge into one lane and use the US 6 (Exit 244) off- and on-ramps to continue on westbound I-70

All work is weather-dependent and subject to change. If weather or unforeseen circumstances impact this work, crews will shift the closure schedule, and the westbound I-70 closures could occur from 9 p.m., Tuesday, Nov. 24, to 5 a.m., Wednesday, Nov. 25.

From early-to-mid December, motorists can expect a series of overnight eastbound I-70 closures at US 6 (Exit 244) for crews to install a movable platform, called a form traveler, at the segmental bridge column over eastbound I-70 near US 6. The form traveler will help crews construct the bridge in segments.

Holiday Travel Hours

There will be no scheduled traffic impacts along eastbound and westbound I-70 from 6 a.m., Wednesday, Nov. 25, through 6 a.m., Monday, Nov. 30, for the Thanksgiving holiday.

The Live Lift Resources

About the Project

The I-70 Floyd Hill Project will improve eight miles of the I-70 mountain corridor, from west of Evergreen to eastern Idaho Springs. The Project will deliver a third westbound I-70 travel lane, which will function as an Express Lane, to improve the current two-lane bottleneck. Other major elements include constructing a missing two-mile section of the frontage road between Evergreen and Idaho Springs, building an eastbound I-70 extended on-ramp for slow-moving vehicles, improving traffic flow and access at interchanges and intersections within the project limits, improving sight distance on roadway curves, improving the Clear Creek Greenway trail, and creating safer wildlife movements.

Construction began in July 2023. I-70 will be in its new alignment in 2028, with the entire project expected to conclude in 2029.

Project Information

For additional information about this project:

Call the project information line at 720-994-2368 (CDOT)
Text floydhill to 21000 to sign up for text alerts
Email the project team at: [email protected]
Visit the project website at: codot.gov/projects/i70floydhill

Know Before You Go

Travelers are urged to “know before you go.” Gather information about weather forecasts and anticipated travel impacts and current road conditions prior to hitting the road. CDOT resources include:

Remember: Slow For The Cone Zone

The following tips are to help you stay safe while traveling through maintenance and construction work zones.

  • Do not speed in work zones. Obey the posted speed limits.
  • Stay Alert! Expect the unexpected.
  • Watch for workers. Drive with caution.
  • Don't change lanes unnecessarily.
  • Avoid using mobile devices such as phones while driving in work zones.
  • Turn on headlights so that workers and other drivers can see you.
  • Be especially alert at night while driving in work zones.
  • Expect delays, especially during peak travel times.
  • Allow ample space between you and the car in front of you.
  • Anticipate lane shifts and merge when directed to do so.
  • Be patient!

Download the COtrip App!

The new free COtrip Planner mobile app was designed to meet the growing trend of information on mobile and tablet devices for the traveling public. The COtrip Planner app provides statewide, real-time traffic information, and works on mobile devices that operate on the iOS and Android platforms. Visit the Google Play Store (Android devices) or the Apple Store (iOS devices) to download!

About CDOT

The Colorado Department of Transportation’s mission is to provide the best multi-modal transportation system that most effectively and safely moves people, goods and information. CDOT maintains more than 23,000 lane miles of highway, more than 3,400 bridges and 35 mountain passes. Our team of employees works tirelessly to reduce the rate and severity of crashes and improve the safety of all modes of transportation. CDOT leverages partnerships with a range of private and public organizations and operates Bustang, an interregional express bus service. Find more details at codot.gov.