I-76 at 96th Avenue

Project Owner CDOT
CDOT Region 6
County Adams
Description of Work Constructs roundabouts at this interchange.
Estimated Total Project Cost $4,004,163
ARRA Funds $2,222,733
Project Status Under Construction- In winter shutdown
Start Date June 22, 2009
Completion Date May 2010
Percentage Spent 75%
Contractor Castle Rock Construction Co.