I-76 at 96th Avenue
- 
          
          
          
          39.870486171 -104.901752472
| Project Owner | CDOT | 
| CDOT Region | 6 | 
| County | Adams | 
| Description of Work | Constructs roundabouts at this interchange. | 
| Estimated Total Project Cost | $4,004,163 | 
| ARRA Funds | $2,222,733 | 
| Project Status | Under Construction- In winter shutdown | 
| Start Date | June 22, 2009 | 
| Completion Date | May 2010 | 
| Percentage Spent | 75% | 
| Contractor | Castle Rock Construction Co. | 