B-4-0 Accept Weekly Payrolls (Certified Payrolls)

The B-4-0 Accept Weekly Payrolls flowchart and process guides listed on this page outlines the responsibilities of the Project Engineer/Project Manager and Region Civil Rights Office within the certified payroll discipline area.
This is a graphic representation of the flowchart for B-4-0 Accept Weekly Payrolls. Text version available below.
Flowchart B-4-0 Accept Weekly Payrolls outlines the roles of the Civil Rights Business Resource Center to setup the project in LCPtracker, the Project Engineer/Project Manager for accepting weekly certified payrolls and the Region Civil Rights Office for conducting a quality control review. Details and information provided in this flowchart is outlined below.


Download B-4-0 Accept Weekly Payroll Flowchart

Flowchart B-4-0: Accept Weekly Payroll

  1. Start: The Civil Rights Business Resource Center (CRBRC) sets up the contract in LCPtracker (Figure 4-1).
  2. The prime contractor and subcontractor enter certified payroll. Go to Flowchart 4A-0, Enter Certified Payroll and Prime Approver Role.
  3. Once the certified payroll has been entered for the prime contractor and subcontractors, the prime approver for the prime contractor approves the weekly certified payroll. Go to Flowchart 4A-0, Enter Certified Payroll and Prime Approver Role.
  4. The CDOT Project Engineer/Project Manager reviews the certified payroll (Figure 4-2).
  5. Decision Item: Is the certified payroll compliant?
    • If yes, the CDOT Project Engineer/Project Manager continues to step 6.
    • If no, the CDOT Project Engineer/Project Manager continues to step 7.
  6.  The CDOT Project Engineer/Project Manager accepts the certified payroll in LCPtracker (Figure 4-4).
  7. The CDOT Project Engineer/Project Manager rejects the certified payroll in LCPtracker (Figure 4-3).
  8. The Region Civil Rights Office performs a quality control review of the certified payrolls (Figure 4-5).
  9. The process ends.

Process Guides

Graphic representation of a clipboard CDOT Civil Rights Business Resource Center

  • 4-1 This process guide is for the use of the Civil Rights Business Resource Center

Graphic Representation of a work vest CDOT Project Oversight

Graphic representation of a briefcase Region Civil Rights Office

  • 4-5 Quality Control Review - to be published