I-25 North Express Link
About the Project
This project on the I-25 North corridor is a continuation of the approximately 26 miles of improvements and expansion that have been completed or are in construction on I-25 between Mead and Fort Collins. This approximately 17-mile project will expand and enhance I-25 from just north of 144th Avenue to CO 66. These segments will connect to 3A (120th Avenue to north of 144th Avenue) and the section currently under construction Segment 5 (CO 66 to CO 56).
Schedule & Important Dates
- Estimated Design Period: Spring 2027 to Fall 2029
- Estimated Construction Period: Spring 2028 to Fall 2033
Project Area
Informational video about I-25 North Express Link (Segments 3B and 4).
Once complete, estimated 2033, this project will complete another expansive stretch of I-25 and provide travelers with a safer, more efficient highway and completing the last link in the Express Lanes between Denver and Fort Collins. This project will also reconfigure CO 7, CO 52 and CO 119 interchanges to improve safety and increase operational capacity.
This project brings economic, environmental and quality of life benefits for northern Coloradans by:
- Making safety improvements to reduce the number of crashes and fatalities
- Decreasing travel time and increasing trip reliability
- Reducing emissions and improving freight efficiency
- Improve congestion and safety
- Rebuilding aging and obsolete infrastructure
- Improving bicycle, pedestrian and transit connectivity
Request for Proposals (RFP) and Scope of Work (SOW)
- Express Link Design RFP - Will be available Dec. 3
- Express Link Design SOW - Will be available Dec. 3
- Express Link CM RFP - Will be available Jan. 12
- Express Link CM SOW - Will be available Jan. 12